Analysis of total productive maintenance (TPM) implementation using overall equipment effectiveness (OEE) and six big losses: A case study
AIP conference proceedings, 1927, 030026 · Published 1 January 2018 · DOI 10.1063/1.5024085
In brief
“Analysis of total productive maintenance (TPM) implementation using overall equipment effectiveness (OEE) and six big losses: A case study” is a 2018 journal article by Zenithia Intan Martomo and Pringgo Widyo Laksono, published in AIP conference proceedings. OpenAlex counts 26 citations as of 15 November 2026, which puts it in the top 9% of works published in 2018 by citations. The publisher's version is not open access, and OpenAlex records no free legal copy.
- Citations
- 26
- Most cited in
- 2021 (6)
- Field-weighted impact
- 11.20
- References
- 4
- Authors
- 2
Abstract
In improving the productivity of the machine, the management of the decision or maintenance policy must be appropriate. In Spinning II unit at PT Apac Inti Corpora, there are 124 ring frame machines that often have breakdown and cause a high downtime so that the production target is not achieved, so this research was conducted… Read the full abstract at the publisher.
Excerpt. This paper is not open access.
Cite this paper
Formatted from the catalogue record. Check names, capitals and page numbers against the paper before you submit.
APA 7
Martomo, Z. I., & Laksono, P. W. (2018). Analysis of total productive maintenance (TPM) implementation using overall equipment effectiveness (OEE) and six big losses: A case study. AIP conference proceedings, 1927, 030026. https://doi.org/10.1063/1.5024085
MLA 9
Martomo, Zenithia Intan, and Pringgo Widyo Laksono. “Analysis of total productive maintenance (TPM) implementation using overall equipment effectiveness (OEE) and six big losses: A case study.” AIP conference proceedings, vol. 1927, 2018, p. 030026. https://doi.org/10.1063/1.5024085.
Chicago
Martomo, Zenithia Intan and Pringgo Widyo Laksono. 2018. “Analysis of total productive maintenance (TPM) implementation using overall equipment effectiveness (OEE) and six big losses: A case study.” AIP conference proceedings 1927: 030026. https://doi.org/10.1063/1.5024085.
Harvard
Martomo, Z. I. and Laksono, P. W. (2018) ‘Analysis of total productive maintenance (TPM) implementation using overall equipment effectiveness (OEE) and six big losses: A case study’, AIP conference proceedings, 1927, p. 030026. doi:10.1063/1.5024085.
IEEE
Z. I. Martomo and P. W. Laksono, “Analysis of total productive maintenance (TPM) implementation using overall equipment effectiveness (OEE) and six big losses: A case study,” AIP conference proceedings, vol. 1927, p. 030026, 2018, doi: 10.1063/1.5024085.
BibTeX
@article{martomo2018analysis,
title = {{Analysis of total productive maintenance (TPM) implementation using overall equipment effectiveness (OEE) and six big losses: A case study}},
author = {Martomo, Zenithia Intan and Laksono, Pringgo Widyo},
journal = {AIP conference proceedings},
year = {2018},
volume = {1927},
pages = {030026},
doi = {10.1063/1.5024085},
url = {https://doi.org/10.1063/1.5024085}
}
Download for a reference manager: BibTeX (.bib) · RIS for Zotero, Mendeley and EndNote (.ris)
Citations by year
| Year | Citations | Share of the best year |
|---|---|---|
| 2019 | 2 | |
| 2020 | 2 | |
| 2021 | 6 | |
| 2022 | 2 | |
| 2023 | 2 | |
| 2024 | 5 | |
| 2025 | 6 | |
| 2026 | 1 |
Its field-weighted citation impact is 11.20: it has been cited 11.20 times as often as the average work of the same field, type and year (1.00 is the world average).
Topic and keywords
Social Sciences › Business, Management and Accounting › Strategy and Management › Management and Optimization Techniques
- total productive maintenance
- overall equipment effectiveness
- six big losses
- machine downtime
- reduced speed losses
- autonomous maintenance
- operator training
- textile industry
Work with this paper
Most-cited papers in Business, Management and Accounting
- Firm Resources and Sustained Competitive AdvantageJay Bryan Barney · Journal of Management · 1991 · 57,081 citations
- The Iron Cage Revisited: Institutional Isomorphism and Collective Rationality in Organizational FieldsPaul DiMaggio, Walter W. Powell · American Sociological Review · 1983 · 42,816 citations
- Building Theories from Case Study ResearchKathleen M. Eisenhardt · Academy of Management Review · 1989 · 39,809 citations
- Firm resources and sustained competitive advantageJay Bryan Barney · Advances in strategic management · 2004 · 38,183 citations
- Absorptive Capacity: A New Perspective on Learning and InnovationWesley M. Cohen, Daniel A. Levinthal · Administrative Science Quarterly · 1990 · 37,030 citations
Questions about this paper
How do I cite this paper in APA style?
Martomo, Z. I., & Laksono, P. W. (2018). Analysis of total productive maintenance (TPM) implementation using overall equipment effectiveness (OEE) and six big losses: A case study. AIP conference proceedings, 1927, 030026. https://doi.org/10.1063/1.5024085
How many times has this paper been cited?
26 times, according to OpenAlex on 15 November 2026. Google Scholar and Scopus count different sets of sources, so their numbers differ.
Is this paper free to read?
OpenAlex records no free legal copy. Check your library's access, the authors' pages or a repository, or ask the corresponding author for a copy.
Who wrote this paper?
Zenithia Intan Martomo, Pringgo Widyo Laksono.
What is the DOI of this paper?
10.1063/1.5024085. The permanent link is https://doi.org/10.1063/1.5024085.
Bibliographic data from OpenAlex (CC0), last checked 15 November 2026. ResearchGuru does not host this paper; the links go to the publisher or the repository that does.